How can I create the Team performance report in Kanbanchi?

You may create the Team performance chart in Kanbanchi. It shows your team members’ progress in getting tasks done. 

To create the team performance chart, open the board you need and switch to Reports by opening the left-side navigation panel, hovering Kanban view and choosing Reports. Click Team performance chart. 

Start with choosing the period of time to create your report, and then choose which users to include to the report.


On the chart, you will see the number of cards that are done in time, past due and the number of cards that aren’t done and therefore are overdue.

Done in time means that they were completed before their due date during the chosen period.
Done past due means that they were completed after their due date during the chosen period.
Overdue means that their due date came during the chosen period and they weren’t completed during the chosen period.
Due means that their due date is within the chosen period.

Also, the overall completion rate is indicated. It shows how many tasks of all due tasks were completed during the chosen period. Also, you will see the performance of each individual user.